Silvertip Blocks 3 & 10
What is Happening?
Block 3
The application for subdivision was approved on October 13, 2020. This created 18 new lots, one spa/resort amenity lot and 17 resort (commercial) accommodation lots.
![]() |
![]() |
Block 10
The application for subdivision was approved on November 24, 2020. This created a residential neighbourhood with 24 duplex lots, 34 detached dwellings, as well as municipal and environmental reserve lots. A condition of this approval is that approved commercial development (i.e. Block 3) must be endorsed or constructed before or at the same time as this development.
![]() |
![]() |
Next Steps - Updated February 23, 2021
- FireSmart tree removal work is currently take place on the site.
- The developer is preparing detailed engineering drawings for review by the Town.
- The developer is working on the outstanding conditions of subdivision.
- Once the conditions have been met, the developer may begin construction.