Nearing the Finish Line for the Cougar Creek Project

Date posted:
The project will be fully operational by Fall 2024
The project will be fully operational by Fall 2024

As Spring arrives in the Bow Valley with much-needed precipitation, we understand that flood risk is a concern for our community. We've resumed our seasonal flood monitoring and are pleased to provide an update on the Cougar Creek project which will increase our community’s resilience to potential future flooding.

Progress:

  • The embankment dam is now 85% complete by volume and on track to reach its full height of 34 m by the end of May. The project is scheduled to fully operational by fall 2024.

Trail Closures:

  • Cougar Creek Canyon and Lady MacDonald Trail will remain closed throughout construction for safety reasons. We know you love these areas and we appreciate your patience. We will announce reopening dates when available.
  • Montane and Horseshoe Trails may experience short closures for blasting usually between 11 a.m. and 3 p.m. These closures will last a maximum of 30 minutes.
  • For details on closures, visit Alberta Parks Advisories.

Next Steps:

  • Construction will continue through the summer. Please adhere to closures and posted signage for your safety.

Learn More:

 